Mar 17, 20221 minMarketing Video & PosterWith symposium around the corner, we've created a poster and marketing video to summarize our project. Check them out below:
Mar 11, 20222 minFinal CrunchThese past two weeks we've been working non stop to get the robot ready for demos. Here's how our progress went: Electrical Last week we...
Feb 19, 20221 minThe Legs are All Assembled!Assembly of mechanical components required for the robot dog to move have just been assembled. The next stages are to create mounts for...
Feb 16, 20221 minLet's Get Moving!With the first leg finished, it was time to start implementing the controls for the legs. Before we can start implementing the walking...
Feb 2, 20221 minIMU, Batteries and JetsonThis week on the electrical side, a large mix of things were done. First a driver was found for the IMU and tested out. This was done by...
Feb 1, 20221 minUsing a Water Jet to Cut Aluminum ComponentsAll of the sheet metal components on the robot are being made with the use of the CNC water jet service offered at the University of...
Jan 28, 20221 minState of the CAD (January)Currently, the bulk of the robot has been designed and has started to be machined. Most of the structural components have been iterated...
Jan 26, 20221 minDetecting LeavesTo be able to detect coffee rust on leaves, our robot must first be able to detect leaves in general. As such, a model was trained on a...
Jan 16, 20221 minThe Parts are Rolling InBefore the winter break, the DS5160 servos were sourced from a vendor on AliExpress. The vendor was actually kind enough to give us a...